Evidence, not fragments

Construction weather evidence for extension-of-time review

Benchmark a project month against historical weather to identify potential qualifying events and prepare editable time-extension evidence for review.

Potential extension-of-time analysis setup with month, historical period, weather criteria and optional contract clause

Benchmark the project period

The EOT Evidence Generator compares a selected month with five or ten years of historical data. It can establish percentile thresholds for configured weather measures and identify days that exceed the resulting benchmark.

  • Five- or ten-year benchmark selection
  • Rain, wind, gust, temperature and snowfall measures
  • Potential qualifying days categorised by breach type
  • Excel data and PNG graphics for supporting records
  • Formatted draft claim-document output
Ten-year August historical weather benchmark showing annual rain, rainy days, wind, gusts, temperatures and snow
The actual ten-year benchmark makes the historical comparison transparent.
Extension-of-time analysis form with a contractor's own weather clause supplied as a screenshot Contract-specific extension-of-time result showing the extracted threshold and all eleven qualifying working days
Supply the project clause in the same guided flow, then review the extracted test and contract-specific qualifying days.

Test the evidence against supplied wording

A weather event does not automatically create entitlement. The relevant contract establishes the test, notice requirements and available relief. The platform can use supplied weather clauses to help structure the analysis and identify events for further review.

Review required: Clause analysis and generated documents are decision-support outputs. Confirm interpretation, causation, notice compliance, critical-path effect and entitlement with suitably qualified project, planning and legal advisers.

From weather event to reviewable evidence

Select the project month

Choose the location and period being assessed.

Set the benchmark

Use the appropriate historical period and configured measures.

Review identified events

Check the source data, thresholds and classification.

Connect event and programme

Add site records, affected activities and programme evidence outside the weather analysis.

A complete extension-of-time submission commonly requires more than weather data, including timely notices, contemporaneous records, programme analysis, causation and compliance with the applicable contract.

Worked example / template

An annotated evidence-pack outline

This is an illustrative outline for a civils weather review — not a real case, not a customer report and not an automatically generated claim. It shows where weather information ends and project evidence begins.

Illustrative evidence-pack contents and annotations
Pack section What the worked example / template shows Boundary and completion note
1. Purpose and scope A blank project brief identifying the review period, location and question being tested. Template only. It does not state that a delay occurred or that relief is due.
2. Weather provenance Source, dataset, requested coordinates, date range, units, retrieval time and the distinction between historical reanalysis, forecast and radar. Weather data is location-based and not a measurement taken at the site. Keep the source context with the export.
3. Assumptions and method Selected benchmark period, trade or weather parameters, thresholds, calendar, timezone and treatment of missing values. Confirm each assumption against the contract and the actual method of work; assumptions are not site facts.
4. Missing data to complete A checklist for site diaries, photographs, daily reports, station records, notices, programme files, activity records and mitigation evidence. A blank or unavailable item remains missing; do not infer it from a weather value.
5. Weather event analysis The dates, parameters and threshold comparisons that identify potential weather events. Weather boundary: this describes weather conditions only; it does not prove an affected activity or delay.
6. Activity impact Placeholders for the planned activity, actual work performed, resources, access, mitigation and contemporaneous site evidence. Activity boundary: the project team must show what work was affected and why the weather mattered to that work.
7. Programme analysis Placeholders for baseline and updates, logic, float, critical path, sequencing, concurrency and mitigation effects. Programme boundary: a weather event is not automatically critical-path delay; a planner must analyse the programme.
8. Clause inputs and entitlement review Contract and clause reference, weather test, notice requirements, relevant dates, causation and relief sought. Entitlement boundary: the platform does not determine automatic entitlement. Contract, project, planning and legal review remains required.
Download the template pack: civils-weather-case-study-pack.docx. It is an illustrative worked example/template, not a real generated report or customer case.
How the data works: The benchmark compares your project month against five or ten years of ERA5 reanalysis — a globally consistent historical record produced by ECMWF and accessible to any independent party. See how thresholds and qualifying events are defined → and how archive and forecast data are sourced →

Related reading

Related features

Construction Weather covers the full project weather cycle — from tender through to extension-of-time evidence.

Tender weather planning

Use ten years of historical data to estimate average unsuitable days by operation and project month at the proposed location.

Historical weather data

Retrieve dated weather records for any project location and export them for reports, delay reviews and project records.

How quantity surveyors use this

See how quantity surveyors use time-extension evidence tools to benchmark project weather, identify qualifying events and build a submission that stands up to scrutiny.

Time-Extension Evidence FAQ

What is an extension of time (EOT) for weather in a construction contract?

An extension of time (EOT) for weather is a contractual mechanism that entitles a contractor to additional time when adverse or exceptional weather conditions have delayed progress. Under NEC contracts this is treated as a compensation event; under JCT contracts it is a relevant event. The contractor must demonstrate that weather conditions exceeded the applicable benchmark, that the work was affected, and that the delay impacted the critical path. A weather time-extension claim typically requires benchmark data, site records, programme evidence and compliance with notice requirements.

How does the EOT Evidence Generator work?

The EOT Evidence Generator compares weather conditions during a selected project month against a five- or ten-year historical benchmark for the same location and calendar period. It uses ERA5 reanalysis data from the Open-Meteo Archive API to identify days on which configured weather thresholds — for rain, wind, frost, snow or other parameters — were exceeded. The tool produces a benchmarked list of potential qualifying events, an Excel weather data export and a formatted draft evidence document for project and contracts team review.

Is ERA5 reanalysis data accepted as evidence in construction contract disputes?

ERA5 reanalysis is produced by ECMWF, an intergovernmental organisation supported by 35 European states, and is one of the most widely cited global climate datasets in peer-reviewed research. It is publicly accessible via the Open-Meteo Archive API, meaning any party can independently reproduce the same figures for the same coordinates and date range. For most construction EOT reviews it provides data that is fit for purpose. For very high-value disputes, a meteorological expert should be instructed to review and supplement the platform data.

What does the time-extension evidence document include?

The generated evidence document records the project location, the benchmark period used, the weather parameters and thresholds applied, and the days identified as potentially qualifying. It is produced as an editable Word document so project and contracts teams can add site records, programme information and causation commentary. The document supports disclosure to the other contracting party and is structured around the information typically required for an extension-of-time submission.

Does the platform automatically establish entitlement to an extension of time?

No. The platform identifies weather events that may qualify under the applicable contract, but establishing entitlement requires more than weather data. A complete EOT submission typically requires timely notices, contemporaneous site records, programme analysis demonstrating critical-path effect, and expert review of causation and contract compliance. The platform's outputs are decision-support information; entitlement must be confirmed with suitably qualified project, planning and legal advisers.

Make weather part of the project plan

Explore construction-focused forecasts, historical records and reporting tools for your next project location.

Try Construction Weather