Tender weather risk

Quantify weather risk before you sign the contract

Underpricing weather risk at tender is one of the most common causes of project losses. Construction Weather gives pre-construction teams the historical data to price it correctly — operation by operation, month by month, at the actual site location.

Tender planning matrix showing historical unsuitable-day data by construction trade operation and project month

The fundamental problem

What weather risk at tender actually means

Every construction programme contains weather-sensitive operations — crane lifts, concrete pours, steelwork erection, earthworks, roofing, painting. Each of those operations has a weather threshold beyond which the work stops. Every day that work stops costs money: plant standing, labour standing, preliminaries running.

Weather risk at tender is the question of who absorbs those costs if the weather exceeds the assumed allowance. Under most standard contracts — NEC3, NEC4, JCT, FIDIC — the risk allocation depends on what was priced in. A contractor who has priced a realistic allowance has a defensible position when delays arise. A contractor who used a generic rule of thumb has absorbed the risk without knowing it.

The problem is not that weather is unpredictable. It is that the historical pattern at each location, for each trade, in each calendar month, is knowable — and most tender teams do not use it.

Tender planning setup controls showing project location, start month and programme duration
Set the project location, start month and duration — the Tender Planning tool retrieves ten years of trade-specific historical data for those exact parameters.

The cost of getting it wrong

What happens when the allowance runs out

A generic weather allowance looks adequate at tender. The problems appear during construction.

Preliminary overruns

Site establishment, supervision, plant and welfare costs continue while weather-affected operations are suspended. When the programme runs long due to weather, prelims overrun the tendered sum without recovery.

Programme compression

Teams accelerate to recover the delay — overtime, additional resources, resequencing. The cost of acceleration is rarely recoverable unless the EOT entitlement was established and the weather risk was correctly allocated in the contract.

Weakened EOT position

An extension-of-time claim under NEC or JCT requires that weather exceeded the applicable benchmark. If the tender did not establish a credible benchmark, the contractual position is harder to defend when delay has already occurred.

The financial dynamic: Weather risk priced at tender is a known, manageable cost. Weather risk absorbed during construction, without contractual cover, is an unplanned loss. The difference between the two is the quality of the data used at bid stage.
Construction Weather platform showing trade advisory output with unsuitable-day data
Trade-specific unsuitable-day counts drawn from ten years of ERA5 reanalysis at the project coordinates.

Quantifying the risk

How to calculate expected unsuitable days per trade

The right starting point for a weather contingency is the historical frequency of unsuitable conditions — by trade, by month, at the actual project location. A concrete operation in January at an exposed coastal site has a different risk profile from the same operation in July in a sheltered urban location.

Construction Weather retrieves ten years of ERA5 reanalysis data for a given location and calculates, for each calendar month, the average number of days on which configured weather thresholds would have been exceeded for the selected trade. This gives the tender team a defensible, independently verifiable starting point for the weather allowance.

  • Ten-year historical average — not a single-year estimate
  • Operation-specific thresholds: wind, rain, frost, humidity, temperature
  • Location coordinates — not a regional or national proxy
  • Month-by-month breakdown matching the programme sequence
  • Exportable for inclusion in tender submission appendices

Building the contingency

From unsuitable-day count to a priced weather allowance

A historical unsuitable-day figure is the foundation, not the complete answer. The contingency calculation also needs to account for how weather loss translates into project cost at this specific project.

Retrieve historical unsuitable days by operation and month

Use ten years of location-specific data to establish the expected frequency of weather-affected days for each weather-sensitive activity in the programme.

Map unsuitable days onto the programme sequence

Assign each calendar month's unsuitable-day figure to the relevant trade operation in the planned programme. Identify where weather-sensitive activities cluster and whether alternative start months improve the weather profile.

Calculate the daily weather cost for each operation

Estimate the daily cost of a weather stoppage for each trade — plant standing, labour, supervision, welfare — and multiply by the expected unsuitable-day count to produce an operation-level weather contingency figure.

Roll up to a total priced weather allowance

Sum across operations to build the total weather contingency. Document the methodology: historical data source, threshold settings, daily cost assumptions and programme assumptions. This documentation supports any future EOT assessment.

Planning limitation: Historical averages describe past conditions and do not predict the exact number of unsuitable days a future project will experience. A well-constructed contingency uses the historical figure as an informed estimate and acknowledges that actual conditions may differ. Climate variability, site exposure and programme flexibility should all be considered alongside the data.

The Tender Planning tool

Historical data structured for tender use

The Tender Planning tool in Construction Weather is built around this workflow. It retrieves and displays ten-year average unsuitable-day counts for the selected trade, location and project month in a matrix that maps directly onto a programme sequence.

Tender teams can compare adjacent months — useful when assessing whether a programme start-date change would improve the weather exposure on a critical operation. The output can be exported for inclusion in tender documents and for audit purposes if the allowance is later challenged.

  • Set project location, start month, year and duration
  • Assign a trade operation to each project month
  • Review ten-year average unsuitable days per month
  • Compare alternative start dates and programme sequences
  • Download data for tender submission appendices
Tender Planning tool →
Tender planning matrix with operations and historical unsuitable-day data arranged by project month
The planning matrix shows ten-year averages by operation and month, ready for export and inclusion in the bid.
How the data works: Unsuitable-day averages are calculated from ten years of ERA5 reanalysis — a stable, reproducible historical record from ECMWF that any independent party can query to cross-check the figures. See how we source and verify the ten-year historical averages →

Related reading

Pricing weather risk at tender stage

A full guide to the methodology — how to translate historical unsuitable-day data into a defensible weather contingency and what to include in the tender submission.

Related features

Construction Weather covers weather risk across the full project lifecycle — from pre-bid planning to extension-of-time evidence.

Tender Planning tool

Walk through the Tender Planning workflow — setting location, assigning operations and reviewing the ten-year unsuitable-day matrix.

Construction weather advisories

Once the project is live, see daily Green, Amber or Red risk gradings for more than 20 trade operations, with hourly drill-down for flagged days.

Early-warning notices

Turn forecast risks into editable early-warning notice drafts — creating the contemporaneous record that supports any future EOT review.

EOT weather evidence

Benchmark a project month against historical data and identify potential qualifying weather events when an extension-of-time claim arises.

Price weather risk before you bid

Use ten years of location-specific historical data to build a defensible weather contingency for your next tender.

Open the Tender Planning tool